Napanee Generating Station


Overview

Napanee Generating Station construction progress.

June 2018 construction progress

Once complete, the $1.2 billion Napanee Generating Station will be capable of producing 900 megawatts of reliable electricity to the people of Ontario. This state-of-the-art plant was designed with the ability to start and stop daily, which means it can vary its output to meet demand. The plant is being built in the Town of Greater Napanee and is expected to contribute roughly $8.4 million a year in direct economic activity to the community.

Learn more at NapaneeGS.com.

$1.2 billion investment
900 MW natural gas generating station
$2 million in community funding

Project timelines

Q1 2012

Contracts executed

2012 – 2014

The Provincial approval process begins alongside preliminary and detailed engineering studies.

2015

Construction starts.

Q4 2018

Contractual Commercial Operation

Economic and community benefits