TransCanada Corporation announced on March 14, 2018, its Cameron Access project was been placed into service in Southwest Louisiana, enhancing the company's ability to deliver North American-produced natural gas to high-value LNG export markets.

Cameron Access involved improvements to existing Columbia Gulf Transmission pipeline, construction of a new compressor station and the addition of 27 miles (43 kilometres) of 36-inch diameter greenfield pipeline. Representing an investment of approximately US$300 million, the pipeline is capable of transporting 800,000 dekatherms a day to the Cameron LNG export facility. The Cameron LNG export facility is currently under construction and scheduled to go into service at the end of 2019.

VIEW NEWS RELEASE

Can transport up to 800 million cubic feet a day of natural gas to LNG facility
Includes 27 miles (43km) of 36-inch-diameter greenfield pipeline