Napanee Generating Station


Overview

Once complete, the $1.2 billion Napanee Generating Station will be capable of producing 900 megawatts of reliable electricity to the people of Ontario. This state-of-the-art plant was designed with the ability to start and stop daily, which means it can vary its output to meet demand. The plant is being built in the Town of Greater Napanee and is expected to contribute roughly $8.4 million a year in direct economic activity to the community.

Learn more on the Napanee Generating Station website.

Project Timelines

Q1 2012

Contracts executed

2012 – 2014

The Provincial approval process begins alongside preliminary and detailed engineering studies.

2015

Construction starts and is expected to last for 32-25 months.

Q1 2018

Contractual Commercial Operation