TransCanada is moving
to a more streamlined process for meter station construction
on our Alberta System.
As of October 1, 2003, the Alberta Energy and Utilities
Board (EUB) will no longer be issuing permits to construct
new meter stations. Consequently, TransCanada will no
longer be required to obtain permits prior to constructing
Alberta System meter stations.
Since the current process up to the actual submission
of an application will remain the same, there is no
significant process change for our customers. In the
event that we receive any objections to a new meter
station that can not be resolved, we would then submit
a non-routine application to the EUB.
For more information about the EUB's change, please
consult Revised
Energy Development Applications and Schedules - Guide
56 or contact TransCanada.