HOLIDAY | VOLUME 06, ISSUE 7
> HOME
> Cartier’s Wind Farm Now Operational

The Baie-des-Sables wind farm went into commercial operation on Nov. 21. One of the largest wind farms in Canada, it provides 109.5 Megawatts (MW) to the Hydro-Quebéc grid.

The project is the first facility Cartier Wind Energy Inc. has completed in the Gaspé region of Quebéc. Cartier Wind Energy is co-owned by TransCanada Corporation (62%) and Innergex II Income Fund (38%).

“The project had an aggressive schedule. We installed 73 wind turbines and the associated facilities in just seven months,” says Corey Goulet, vice-president, Project Implementation. “I’m very proud of the project team for meeting the challenge and reaching this milestone.”

“The success of the project required the cooperation of our partners, outside resources and the community,” says Philippe Piuze, project manager, Cartier Wind Energy.

Work on the wind farm began in March 2006 and at the peak of construction 250 workers were on-site. “Although everyone was focused on delivering the project on time, safety was always the top priority,” says Catherine Pineau, construction manager, Cartier Wind Energy.

“Delivering the 110 foot blades to the site was one of the biggest risks we faced,” says Stephanie Wilson, manager, Project Implementation. “The blades were transported from the factory during peak tourist season, approximately 450 kilometres away. The Cartier project team, GE, the Ministry of Transportation and the Quebéc tourism bureau worked collaboratively to ensure transportation was done safely.”

Baie-des-Sables was publicly inaugurated on Dec. 1, 2006. With a total investment of $1.2 billion over seven years, Baie-des-Sable is the first of many important investments for Cartier and will help Quebéc meet future energy demand needs.

For more information, contact Stephanie Wilson at 403.920.5061.

What it takes to install a wind turbine
  • Turbine parts are delivered to the site.


  • A heavy lift crane is used to assemble the tower sections.


  • Once the tower is erected, the nacelle (the structure that houses the key components of the wind turbine including the rotor shaft and generator) is installed at the top. Workers are situated inside and outside of the tower to make sure it’s put in the right spot.


  • The rotor and blades are assembled on site and lifted onto the nacelle. Weather conditions are critical at this stage of construction - it would be dangerous if wind caught the blades.


  • Once the turbine is assembled, additional work is done to connect the turbine to the electrical grid and commission the unit.
 
>> RECEIPT POINT APPLICATION
>> IGUA CONFERENCE
>> PIPELINE OPENS IN MEXICO
>> CARTIER’S WIND FARM
>> PNGTS AGREEMENT
>> MAPLE LEAF BALL
 
    Copyright © 2006 | Legal Notice Get Acrobat Reader
DATE: December 19, 2006